Outreach and Project Milestones

Complete

  • 9/20/25 - Public Workshop 1 - Aesthetics & Architecture. Download meeting summary and materials.

  • 8/9/25 - Introductory Postcard mailed to community. Download postcard.

  • 7/31/25 - Planning Commission Initiation Meeting
    Initiation is the first official step in the process. At this meeting, Planning Commission decides whether the proposed idea is worthy of further analysis. Initiating the process gives city staff the green light to start allocating time and resources to application review.

  • 7/25/25 - Launch of community website

  • 7/8/25 - SRCA Presentation. View slides.

  • 7/3/25 - SRPG Initiation Recommendation. View slides.
    Supporting Initiation does not indicate support for the project. Lots of outreach and technical review has to take place before the SRPG will make an official decision on whether to support the project.

  • 4/28/25 - Submission of Initiation Letter. Download letter.

  • 4/8/25 - Scripps Ranch Civic Assn. (SRCA) Intro meeting

  • 3/6/25 - Intro at Scripps Ranch Planning Group (SRPG)

  • 2024 - Due diligence, property research


Projected Milestones (subject to change)

Q3

  • 9/10/25 - Workshop 2: Circulation

Q4

  • 10/28/25 - Workshop 3: TBD

  • Site Planning and Technical Studies

2026

  • January - Open House

  • January - Formal Application Submittal

  • Spring - CEQA Scoping Period

2027

  • Public Review of Draft EIR

  • SRPG

  • Planning Commission

  • City Council